TR EN

🇹🇷 Düzce, Türkiye

Gönenç Alüminyum

Press-exit handling and conveyor / run-out line at the Düzce plant — 1,800 tonf.

Installed line

Conveyor / run-out line1,800 tonf
Gönenç Alüminyum — plant view, Düzce, Türkiye

Installed equipment

Installed equipment

  • Conveyor / run-out line — 1,800 tonf

About this project

About this project

Press-exit handling and conveyor / run-out line at the Düzce plant — 1,800 tonf. The line was installed with ADA TRUSTAR’s engineering and project coordination, and commissioned within the scope of handling / conveyor.

The list below states the equipment installed at this plant exactly as recorded in the portfolio:

  • Conveyor / run-out line — 1,800 tonf

The 1 photographs on this page were taken on site during installation and commissioning. If you share your capacity, alloy and profile range for a similar line, we prepare a technical specification with the same approach.

ADA TRUSTAR scope

Line layout preparation, run-out and conveyor sizing matched to the press capacity, equipment supply, installation and commissioning follow-up.

This record was imported from the ADA TRUSTAR project portfolio (ref. ATX / 2025). The photographs were taken on site.